The City of Gainesville’s 2018-2020 efforts include the following improvements at the Hippodrome:
First and Second Floor Lobbies:
New flooring, doors and door frames, wood trim, countertops, paint, new lighting and fixtures and restoration and relocation of existing historic light fixtures. $196,562
Exterior Lighting:
Replacement and upgrades to exterior and front porch LED lighting. $49,872
Building Exterior:
Replacement of the box office window, an exterior steel door and repair to the building’s gutter lining. $9,364
Interior Lighting:
New office, general and theatrical lighting for the first and second floor. $32,440
Accessibility Improvements:
New ADA assistive listening systems for the main stage and cinema. New stair nosing for the auditorium and upgraded second floor handrails. $9,603
Air Conditioning:
Replacement of units on the first floor and basement green room, and first-time installation of an air conditioning system in the scene shop. $21,627
Speaker System:
New speaker system for the second floor. $4,910
Joyner Construction Partners, LLC was the general contractor for the project. For more information, please contact Betsy Waite, project manager, at 352-393-8187 or waiteed@gainesvillefl.gov.